As with all construction projects, the timeline may fluctuate. We will make every effort to keep this timeline up to date but please note that this schedule is subject to change. To confirm the project schedule and receive more details as to how your stay may be impacted, please call (760) 434-7020.

Week # Dates Units Impacted Expected Impact
42 – 45 10/16/22 – 11/13/22

110, 111, 112, 210, 211, 212

Owners of  310, 311, 312 will be relocated to another unit on property

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.

 

44 – 47  10/30/22 – 11/26/22

113, 114, 115, 116, 213, 214, 215, 216

Owner of  313, 314, 315, 316 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
46 – 49 11/13/22 – 12/10/22

117, 118, 119, 120, 217, 218, 219, 220

Owner of  317, 318, 319, 320 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
48 – 51 11/27/22 – 12/24/22

101, 102, 103, 201, 202, 203

Owner of  301, 302, 303 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
50 – 1 12/12/22 – 1/7/23

104, 105, 106, 107, 108, 109, 204, 205, 206. 207, 208, 209

Owner of  304, 305, 306, 307, 308, 309 will be relocated to another unit on property.

Pool will be unavailable. Noise, vibration, dust and smell from construction equipment.  Access to Elm Building will be redirected. Construction work to the North side of Elm Building planters.
Week # Dates Units Impacted Expected Impact
36 – 39 9/12/23 – 10/6/23

121, 122, 123, 124, 221, 222, 223, 224

Owners of  321, 322, 323, 324 will be relocated to another unit on property

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.

 

38 – 41  9/26/23 – 10/20/23

125, 126, 127, 128, 225, 226, 227, 228

Owner of 325, 326, 327, 328 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
40 – 43 10/9/23 – 11/3/23

129, 130, 131, 132, 229, 230, 231, 232

Owner of 329, 330, 331, 332 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
42 – 45 10/24/23 – 11/17/23

133, 134, 135, 136, 233, 234, 235, 236

Owner of 333, 334, 335, 336 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
44 – 47 11/7/23 – 12/1/23

137, 138, 139, 140, 237, 238, 239, 240

Owner of 337, 338, 339, 340 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.
46 – 49 11/21/23 – 12/15/23

141, 142, 143, 144, 241, 242, 243, 244

Owner of 341, 342, 343, 344 will be relocated to another unit on property.

Work on roof with scaffolding around 1st and 2nd floor units and limited access to balconies.  Noise, vibration, dust and odor from construction equipment.